Thursday 23 October, 2025
Preparatory work Pussen Pavilion
Adapteo and NCC will place the crane inside the work area that they have fenced in. See updated APD plan.
Monday 29 September, 2025
Groundworks begin next to the Pussen Pavilion
The ground works will continue during weeks 40 and 41 in connection with the Pussen Pavilion. After that, the next stage of foundation work will begin.
Wednesday 24 September, 2025
Information letter week 39-40 2025
The Pussen projectWeek 39Assembly of steel details for bridges and wooden decks and construction of decking on wooden decks and bridges. Laying of slabs and friezes. Casting of pillar shafts for barbecue huts.Week 40Continued construction of decking on wooden decks and bridges. Installation of barbecue huts, adjustment for grass areas, laying of tiles and planting of perennials.Preparatory work of the PavilionIn connection with preparatory work for the upcoming construction of the Pussen pavilion, ground work will begin at the end of week 38/beginning of week 39. The work will involve some disruption in the area. The parking lot, which is marked on the map below, will be cordoned off with construction fencing to create a work area. The cordoning off will take place in the middle/end of week 38 and will apply throughout the construction period. The lighting in the parking lot has already been taken down. Four lighting posts have been removed and only one post at the beginning of the parking lot is in operation. This means that the parking lot will be unlit until it is cordoned off. The first works include preparatory ground work for water, electricity and fiber. This will be followed by work to lift there and establish the new Pussen pavilion.
Wednesday 24 September, 2025
Information letter week 39-40 2025
Students' HouseAdjustment of all windows in staff room D2148
Wednesday 24 September, 2025
Information letter week 39-40 2025
House FPeab is repairing the floor in F441A and repairing a window in F434.The lighting replacement in the long corridors is complete.Peab is also fixing the leak in the culvert between the E and B buildings.
Wednesday 24 September, 2025
Information letter week 39-40 2025
House ERecurring blockage in toilet group, E646. The drain needs to be checked. To be fixed by Peab/Bravida.
Wednesday 24 September, 2025
Information letter week 39-40 2025
House CParkkompaniet has been commissioned to straighten and reinforce the scraper grates at the entrances.Planning for replacing the lighting in the light courtyard has begun.
Wednesday 24 September, 2025
Information letter week 39-40 2025
House BetaLeak in the library - NCC begins troubleshooting on 19/9.Troubleshooting of solar shading is in progress.
Wednesday 24 September, 2025
Information letter week 39-40 2025
ALFA HouseWork to replace ventilation units and other technical equipment in the ALFA building is ongoing.This can cause disturbing noise both during the day and evening, as well as an increased presence of contractors in the corridors. The fan room is starting to get ready soon.Adjustments and completion are underway.Insulation of cooling pipes in the corridors connecting the technical room and the fan room in Building A is still ongoing.The ventilation and heating are back on and fully operational. The project should be fully completed by the beginning of October.
Tuesday 23 September, 2025
Information letter week 39-40 2025
House AInstallation of solar cells is underway on the A-house. Work is primarily on the roof, but some installation is taking place inside the house as cabling will be done from the basement level to the roof. A stair tower has been erected at the facade of the A-house, between the A-house and the Teknikens Hus. When delivering materials, we use a crane truck or mobile crane and block off when lifting.Minor work and improvements will also be carried out in the house in the coming weeks.